Which sequence correctly describes the steps for slump testing the delivered concrete?

Prepare for the ACI Concrete Transportation Inspector Test. Access flashcards and multiple choice questions with detailed hints and explanations. Boost your confidence for the exam!

Multiple Choice

Which sequence correctly describes the steps for slump testing the delivered concrete?

Explanation:
The test measures concrete’s workability by how much its height changes when the slump cone is removed, so the steps must establish a consistent starting point and uniform compaction before removing the mold. Start by taking a representative sample and placing the slump cone on a flat, non-absorbent surface. Fill the cone in three equal lifts, ensuring each layer is firmly compacted to eliminate air pockets. After the cone is fully filled and each layer compacted, strike off the excess concrete level with a straight edge to create a clean, level top. Then lift the cone away smoothly and vertically, without twisting, and measure how far the concrete subsides—the slump. This sequence yields a reliable measure of workability because the three-layer fill and per-layer compaction produce a uniform sample, the strike-off provides a defined starting height, and lifting the cone without disturbance gives an accurate height change. The other options mix up the order or omit important steps: striking off before filling doesn’t establish the correct initial surface, measuring before lifting ignores the actual slump, and compacting only the bottom layer fails to produce a representative sample.

The test measures concrete’s workability by how much its height changes when the slump cone is removed, so the steps must establish a consistent starting point and uniform compaction before removing the mold. Start by taking a representative sample and placing the slump cone on a flat, non-absorbent surface. Fill the cone in three equal lifts, ensuring each layer is firmly compacted to eliminate air pockets. After the cone is fully filled and each layer compacted, strike off the excess concrete level with a straight edge to create a clean, level top. Then lift the cone away smoothly and vertically, without twisting, and measure how far the concrete subsides—the slump. This sequence yields a reliable measure of workability because the three-layer fill and per-layer compaction produce a uniform sample, the strike-off provides a defined starting height, and lifting the cone without disturbance gives an accurate height change.

The other options mix up the order or omit important steps: striking off before filling doesn’t establish the correct initial surface, measuring before lifting ignores the actual slump, and compacting only the bottom layer fails to produce a representative sample.