What action is required if the discharge chute becomes clogged during transfer of concrete?

Prepare for the ACI Concrete Transportation Inspector Test. Access flashcards and multiple choice questions with detailed hints and explanations. Boost your confidence for the exam!

Multiple Choice

What action is required if the discharge chute becomes clogged during transfer of concrete?

Explanation:
When a discharge chute becomes clogged, the priority is safety and control of the concrete flow. Stop the discharge and clear the obstruction using proper, safe procedures, then resume only when the flow is restored. This prevents back-pressure, spills, and potential injuries from sudden release or improvised attempts to dislodge the blockage. After clearing, verify the chute is clear and the concrete is flowing smoothly before restarting. Shaking the truck or continuing at a reduced rate without clearing, or simply notifying the producer and proceeding, does not address the immediate hazard and can lead to equipment damage or unsafe conditions.

When a discharge chute becomes clogged, the priority is safety and control of the concrete flow. Stop the discharge and clear the obstruction using proper, safe procedures, then resume only when the flow is restored. This prevents back-pressure, spills, and potential injuries from sudden release or improvised attempts to dislodge the blockage. After clearing, verify the chute is clear and the concrete is flowing smoothly before restarting. Shaking the truck or continuing at a reduced rate without clearing, or simply notifying the producer and proceeding, does not address the immediate hazard and can lead to equipment damage or unsafe conditions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy